Communities · Hatta, Dubai · Apr 2018

Community-scale rollout

kWp

Hatta 330 Villas: rooftop, 330 homes solar

The site and the brief

A whole mountain community, 330 villas, delivered as one project.

The client wanted to cut daytime grid consumption without interrupting operations. SOLEC surveyed the rooftop, 330 homes areas, checked the structure and the DEWA connection, and designed a system sized to the site's load profile, so almost all of its output is used on site.

The system

4.8 kWp on each villa, across 330 homes.

Modules
Bifacial mono PERC, 550 Wp
Inverters
String inverters, 8 × 125 kW
Mounting
Rooftop, 330 homes
Monitoring
24/7 remote monitoring, SCADA

How SOLEC delivered it

  1. 01 Assessment and planning 6 weeks Feasibility studies · Solar radiation calculations · Grid connectivity evaluation
  2. 02 Engineering and design 8 weeks Structural layout · PV array optimisation · Battery specification
  3. 03 Construction and commissioning 14 weeks Site delivery · System erection · Diagnostics and grid synchronisation
  4. 04 Operations and maintenance Ongoing SCADA monitoring · Local technicians · Predictive optimisation
How we deliver →

Results

  • 2,614MWh

    Clean energy a year

  • 1,046t

    CO₂ avoided a year

  • 4.5years

    Expected payback